3T Additive Manufacturing now draws around 70% of its revenue from production and repeat orders, commercial director Eddie Andrews says, five years after the Newbury company reset how it took on work. New product introduction still takes up roughly 80% of the team's time.
Andrews joined in November 2021, when the business could make a one-off metal part for any of hundreds of customers but struggled to win the order to make the same part again at an agreed price and on schedule. "How do you make that boring?" he recalled. "How do you make that general manufacturing?"
Machines bought against orders
The order book for its EOS metal printers shows the shift. Previously 3T-AM might have bought an M400 to trial a different material and see what business it could develop; now, Andrews says, customer programmes account for the capacity of incoming machines before they reach the factory.
Semiconductor customers generate the strongest demand, followed by energy, then space and defence. Aerospace remains central to the company's plans, but 3T-AM has found work for its machines while it waits for more aerospace programmes to reach suppliers at volume.
From prototypes to process control
Andrews dates the business to 1997 and its first metal machine to around 2008. By the 2021 reset, years of accommodating individual prototype jobs had left process after process on the shop floor. The company narrowed its customer base, gave larger accounts more influence over development and simplified accumulated procedures, with much work still manual while the team established which operations it could reliably repeat.
Responsibility for a job changed as much as the equipment. When the first person to see a drawing was the engineer who printed it, the question was simply how to print it. Today a product owner delivers the finished component, and print and machining specialists agree the condition a part should be in as it passes between operations.
"To become a successful additive manufacturer, you need to be a really good CNC machining company," Andrews says. Bringing machining in-house gave the SME more control over cost, quality and delivery dates, while larger multi-laser machines improved printing productivity. Neither alone could tell a customer when a finished part would arrive.
The commercial transition was harder to time. Production orders rose and then tapered off, and turning away too much prototype work in the upswing would have left gaps when it eased. Repeat orders now let 3T-AM choose which development jobs to take; some will never become production contracts, but "if you don't take part in the journey, you're never going to find out."
SBO ownership and expansion
Austrian precision manufacturing group SBO acquired 3T-AM in October 2025; the Newbury business had generated around £5 million in sales in 2024. SBO brought experience machining downhole drilling equipment, including components up to ten metres long, and interest in 3T-AM's metal printing expertise and its different industrial customer base.
SBO approved the five-year plan and asked whether it could be delivered quicker. In August 2026 the group reported that 3T-AM had added an EOS M400 in the second quarter, ordered another printer and invested further in post-processing, part of a seven-printer expansion across UK and US operations.
A full order book makes the next machine easier to justify, but leaves little time on it to qualify a different material or develop a new product. Andrews wants to keep two reasons to invest: contracted demand, and the work 3T-AM cannot yet offer.
A pre-pandemic aerospace enquiry illustrates the scale. A single family of parts would have required 16 multi-laser systems to cover only a share of the requirement, and the buyer's question was how many suppliers had the floor space, capital and capacity — one reason, Andrews suggests, why original equipment manufacturers still keep sizeable additive programmes in-house.
What the customer can measure
For some customers a printed part replacing a casting earns its keep through lead time alone, even at much the same unit cost. At higher volumes the calculation tightens: maintenance contracts and consumables weigh on the hourly rate, and a single-shift factory has fewer productive hours over which to spread them. Andrews sees scope to learn from CNC shops running around the clock, and points to support removal as a candidate for automation.
A Honeywell Aerospace project will test another claim. Under an Aerospace Technology Institute-funded programme, the partners are converting a conventionally manufactured component to additive, while the sustainability team at the NCC in Bristol runs a 12-month life-cycle assessment covering manufacture, service and end of life. Printing closer to finished shape should use less feedstock and leave less metal to machine away than billet; the study compares both routes alongside in-service benefits.
The intended outcome in Newbury is something a purchasing department could use. As 3T-AM connects factory and enterprise systems, it is developing digital product passports documenting the carbon associated with making an individual component. By the end of 2028 Andrews wants that information to accompany every part at no extra charge.