In central Paris, a Liebherr MK 88-4.1 mobile construction crane operated by the Ponticelli group repaired a historic bridge and reinstalled a damaged artwork on the Pont-Neuf. The crane was used to repair the art installation La Caverne du Pont-Neuf, created by French artist JR. The temporary work pays tribute to Christo and Jeanne-Claude's 1985 wrapping of the Pont-Neuf. The inflatable structure is about 120 metres long. In early June, violent gusts of wind and hail damaged parts of its outer shell.
Ponticelli, a French lifting and industrial services company, developed a lifting solution within hours. Louis-Arthur de Quatrebarbes, head of the handling and lifting agency at Ponticelli, said the team was on site a few hours after the damage occurred to work out the best technical solution with the client. He added that in addition to repairing the tarpaulin, the team had to carry out a safe lifting operation in almost constant wind and under considerable time pressure.
Confined heritage site
The Pont-Neuf is Paris's oldest bridge and offers limited space for work while welcoming many daily visitors. The team used load-distribution plates to reduce ground pressure and applied safety and traffic management measures. Initially, the team planned to use a larger Liebherr mobile crane. Because of the tight conditions, the MK 88-4.1 was moved in. Its 45-metre trolley jib could reach all damaged areas, and its four-axle design allowed relocation from one side of the bridge to the other, where storm damage also occurred. Short set-up time and a compact outrigger system further supported the operation.
Night shifts and precision
The crane cab could move at working height, giving the operator a clear view of the approximately 18-metre-high structure and the rope access technicians. Boom-mounted spotlights lit the work area during night operations. Repairs took place over four night shifts. Damaged fabric sections weighing between 200 and 400 kilograms were lifted and reattached in collaboration with rope access technicians. Because the site sits in a wind corridor along the River Seine, weather conditions were monitored continuously. The crane operator and rope access technicians communicated by radio throughout.
Before work began, the team carried out site inspections, load calculations, and collision analyses of surrounding buildings. A 360-degree test then confirmed the planned crane positioning.
For Ponticelli, the project went beyond a conventional lift. De Quatrebarbes said the company was proud to have been part of the work of art, and cited JR's view that installing the artwork is part of the artwork, adding that the crane was also part of it. He described the visually striking deployment of the MK crane as a magical moment.
With the Pont-Neuf deployment, the Liebherr MK 88-4.1 demonstrated its suitability for demanding inner-city projects. Where heritage conservation, confined spaces, and precision meet, the mobile construction crane offers a combination of reach, compactness, and flexibility, according to the company.