Introducing a new menu item depends on getting the right equipment into every location, and that work begins well before the dish reaches the plate. Bryan Musgrove, divisional senior director on national accounts at TriMark USA, has supported many equipment rollouts for new menu items and shared practices aimed at making them run more smoothly.
His first recommendation is a rollout playbook that covers each site. In one project, a brand needed new toasters so it could add toasted sandwiches to a breakfast lineup that already included biscuits and wraps. The obstacle was not the equipment but the buildings: some locations had electrical capacity that was already maxed out, while small mall or urban sites lacked the counter space for a toaster. In those cases the operator had to create room by adding shelving or an extra table, a change that affects workflow. The playbook sets out which locations are plug-and-play and which need additional support.
Schedule from supplier lead times
Second, the schedule should be built from the manufacturer’s lead time. A supplier may confirm it can produce 200 units without saying how long that takes; at 10 units a week, the order runs 20 weeks. The same supplier might hold inventory for the first 50 units, then need eight weeks to bring in parts sourced overseas before finishing the remainder. Lead time, rather than the campaign calendar, is what determines what is achievable. When an item launches alongside marketing tied to a particular season or occasion, Musgrove’s advice is to work backward from the desired launch date and build a timeline that can actually be met.
Consolidate packaging for delivery
Third, delivery logistics can be simplified by changing how goods are packed. Rather than shipping smaller wares straight to each location in their original boxes, Musgrove suggests asking the dealer to consolidate and repackage the items into one package per site. For one brand adding macaroni and cheese to its sides lineup, the rollout required visual holding cabinets, pans and serving scoops in varying sizes. TriMark packed those items into a single package per location, with instructional materials and exterior labeling so managers knew exactly what they were receiving when it arrived.
Taken together — deciding which locations need more support, scheduling to realistic lead times and simplifying deliveries — the three practices address site readiness, supplier capacity and last-mile logistics. Musgrove presents them as the route to a smooth rollout; run as planned, he says, the new menu item can generate buzz and increase traffic.
